February 24, 2026 City Council Meeting
--- date: 2026-02-24 governing_body: City Council meeting_type: Regular Meeting location: Lawton City Hall, Wayne Gilley Auditorium start_time: 6:00 PM duration: 5:15:12 public_video: https://www.youtube.com/embed/pQHHHzGMiRc ---City of Lawton — City Council Meeting
Date: February 24, 2026
Time: 6:00 PM
Location: Lawton City Hall, Wayne Gilley Auditorium
Attendance
City Council Members Present
- Roll Call: TBD
Quorum: Yes
Absences: TBD
Agenda / Packet / Minutes
- Agenda: City Council Agenda — February 24, 2026
- Packet: TBD
- Minutes: TBD
Summary
The February 24, 2026 City Council meeting included presentations and routine consent items, followed by extended debate over a zoning ordinance for data centers and digital asset mining, a discussion about the future scope of the Library of Tomorrow committee, a status report on the Gore Boulevard traffic signal project, and executive session on pending legal and personnel matters.
The most consequential legislative action of the night was approval of a revised data center / digital asset mining ordinance on a 5–3 vote, after extensive discussion about state law limits, water availability, electrical capacity, and how much control the city could retain over future large-scale development. Later in the meeting, council dissolved the existing Library of Tomorrow committee and reconstituted its work under a clarified mission and new chair on an 8–0 vote.
Opening Proceedings
Call to Order / Invocation / Pledge of Allegiance
- Start: TBD
- Action: Meeting called to order; invocation and pledge conducted
- Vote: N/A
Roll Call
- Start: TBD
- Action: Roll call conducted; quorum established
- Vote: N/A
Presentations
Item 1 — Defense Community Champion Award presented to Mayor Stanley Booker
- Start: TBD
- Action: Presentation
- Vote: N/A
Item 2 — Clean Sweep Award — Combat Veterans Motorcycle Association OK 10-3
- Start: TBD
- Action: Presentation
- Vote: N/A
Item 3 — Recognition of Eisenhower Middle School’s Media Class
- Start: TBD
- Action: Presentation / recognition
- Vote: N/A
Item 4 — Recognition of 25 Years of Service (Oklahoma Municipal League)
- Start: TBD
- Action: Presentation / recognition
- Vote: N/A
Reports
Mayor / City Council / City Manager Reports
- Start: TBD
- Action: Reports given
- Vote: N/A
Consent Agenda
All items listed below were considered routine and scheduled for a single motion unless removed for separate consideration.
Consent Agenda
- Start: TBD
- Action: Consent agenda considered
- Vote: TBD
- Notes: Earlier transcript portion not visible in current excerpt
Item 5 — Damage Claim Recommended for Denial
- Claimant: Michael Cowing
- Amount: $750.00
- Vote: TBD
Item 6 — FYE26 Budget Amendment (Medicine Park Water Treatment Plant Roof)
- Amount: $1,127,193.02
- Action: Reduce transfer from Enterprise Fund to General Fund and appropriate funds for roof replacement
- Vote: TBD
Item 7 — Rogers Lane Lighting Project
- Contractor: TLS Group, Inc.
- Amount: $1,487,501.50
- Vote: TBD
Item 8 — Pavement Maintenance Program Management Task Order Supplement
- Consultant: WSB
- Amount: $130,500
- Vote: TBD
Item 9 — Park Modernization Lighting Project Contract Extension
- Vendor: First Light of Tulsa
- Vote: TBD
Item 10 — Change Order No. 2: SW 11th St Bridge / Wolf Creek Project
- Contractor: Sewell Bros, Inc.
- Action: Add 40 calendar days
- Vote: TBD
Item 11 — Amendment No. 13: Garver, LLC
- Amount: Not to exceed $584,100
- Project: Industrial water main replacement along Goodyear Blvd
- Vote: TBD
Item 12 — Amendment No. 13: Jacobs Engineering Group, Inc.
- Amount: Not to exceed $913,417
- Project: Industrial High Zone Booster Pump Station / West High Zone Pump Station No. 3
- Vote: TBD
Item 13 — Replat of Lot 3A, Bilbrey’s East Plaza Part One
- Location: North of SE Lee Blvd and east of SE 36th Street
- Vote: TBD
Item 14 — Underground Right-of-Way Easement to PSO
- Project: FISTA-related project south side of the mall
- Vote: TBD
Item 15 — As-Built Drawings and Maintenance Bond: Scissortail Point Development
- Location: South side of NW Cache Road between NW 47th Street and NW 53rd Street
- Vote: TBD
Item 16 — Fence Height Waiver for FedEx
- Location: 1813 SW 11th Street
- Action: Allow 12-foot screening fence instead of 8-foot maximum
- Vote: TBD
Item 17 — Council Policy 04-09: Customer Water Usage Discrepancies
- Vote: TBD
Item 18 — Amendment to Council Policy 8-01: Engineering and Architectural Selection Process
- Vote: TBD
Item 19 — FY2027 Oklahoma Highway Safety Office Grant Application
- Amount: Up to $425,000
- Vote: TBD
Item 20 — Donation to Lawton Public Library
- Donor: Carnegie Corporation of New York
- Amount: $10,000
- Vote: TBD
Item 21 — Claims List Approval
- Period: December 8, 2025 through February 20, 2026
- Vote: TBD
Item 22 — Appointments to Boards and Commissions
- Vote: TBD
Item 23 — Approval of Minutes
- Meeting: February 10, 2026
- Vote: TBD
Unfinished Business
Item 24 — Data Center / Digital Asset Mining Ordinance
- Start: 02:29:38 (YouTube)
- Action: Public discussion and ordinance consideration regarding data centers / digital asset mining uses in industrial districts
- Vote: 5–3 (passed)
- End: 02:59:34 (YouTube)
- Notes:
- Council and staff discussed the city’s limited control over development outside city limits and the distinction between water sold by agreement outside city limits versus groundwater rights.
- Public Utilities staff explained that under the Arbuckle-Timbers Aquifer framework, landowners may obtain roughly 2 acre-feet per acre per year, and estimated that about 260 acres would be needed to support 1 million gallons per day.
- Staff and legal discussion emphasized that state law defines digital asset mining around a greater-than-1-megawatt threshold, which constrained how restrictive the city could safely be without increasing litigation risk.
- Mayor Booker framed the issue repeatedly as one of maintaining city control.
- Motion text, as read into the record, amended the ordinance to:
- allow digital asset mining / data centers with peak electrical demand not greater than 2 megawatts in I-1 subject to written clearance from the local electrical provider; and
- require use permitted on review in I-4 for digital asset mining / data centers with peak electrical demand greater than 2 megawatts, also subject to utility clearance;
- delete Sections 3 and 4 entirely.
- Discussion included concerns about:
- water demand,
- electrical infrastructure,
- long-term job creation,
- abandoned facilities,
- state legislative gaps,
- and whether the city could require review for every size category.
- Staff stated that under the current code, without amendment, a qualifying use could potentially proceed in industrial zoning with far less council control.
- The revised title of the ordinance was read beginning at 02:57:13.
- Vote confirmed at 02:59:27 and announced as passed 5–3.
- Mayor Booker also directed staff to return with additional recommendations to help the city maintain control going forward.
Related Video — Public Comments Clip
Public Comments Clip: Watch on YouTube
This clip contains the unedited public comments from the February 24, 2026 Lawton City Council public hearing on proposed zoning changes for data centers / digital asset mining.
Topics raised by speakers included:
- Water use and infrastructure
- Electrical demand
- Noise and neighborhood impacts
- Environmental concerns
- Economic development questions
- Alternative site proposals, including FISTA
Agenda Reference: Item 24 — Data Centers / Zoning
Council Vote on Ordinance: Passed 5–3
Yes: Hooten, Brown, Epps, Williams, Warren
No: Hampton, Dimery, Weger
Note: The city camera overlay may display an incorrect date. The recording is from the February 24, 2026 City Council meeting.
Business Items
Item 25 — Library of Tomorrow Committee Update
- Start: 03:09:09 (YouTube)
- Action: Committee update received; committee structure and scope discussed; committee dissolved and reconstituted under clarified mission
- Vote: 8–0 (passed)
- End: 03:40:20 (YouTube)
- Notes:
- Committee leadership reported that the original mission had become muddled and that the conversation drifted into defending the library rather than conducting a structured long-range evaluation.
- Chair reported approximately $6 million in identified and suspected needs, but stressed that many figures were preliminary and not derived from a full architectural / engineering assessment.
- Concerns raised included:
- concealed building conditions,
- possible mold or moisture intrusion,
- code compliance gaps,
- long-term service model changes,
- digital versus in-person library use,
- and whether the city should invest heavily in an aging facility without clearer long-term planning.
- An initial motion beginning at 03:25:04 sought to disband the current committee and create a new Library Facilities Review Committee with a fact-finding mission extending conceptually through 2075. That motion died for lack of second at 03:27:07.
- A new motion then followed to keep the same committee but clarify the mission. During discussion, the mayor requested a friendly amendment to install Kirby Brown as chairman.
- A further amendment clarified dissolution of the original time-limited Library of Tomorrow Committee and re-establishment of the work under the updated mission.
- Public-facing distinction discussed on the record:
- daily library operations remain with the director / library board;
- this committee’s role is broader capital and future-planning review.
- Final vote passed 8–0 at 03:40:20.
Item 26 — Gore Traffic Lighting Project
- Start: 03:40:26 (YouTube)
- Action: Status update received from Public Works
- Vote: N/A
- End: 03:45:47 (YouTube)
- Notes:
- Public Works reported that initial CMAQ-related funding had been approved later than first projected, with usable funds available by January 23, 2026.
- Staff stated the initial $50,476 scenario had been funded and equipment ordered, including:
- GPS timing units,
- electrical wiring,
- signal heads,
- and related controller upgrades.
- Additional funds had also been committed toward the next phase because those funds would otherwise expire.
- Staff stated the first equipment was expected in April 2026, with implementation targeted before June 1, 2026.
- Mayor Booker pressed for:
- a full council report at the next meeting,
- intersection-by-intersection ranking information from the WSB report,
- and a clearer connection between spending and anticipated traffic-flow improvement.
- On the record, staff affirmed the first phase was intended to improve traffic flow by roughly 25% once equipment was installed.
Executive Session
Item 27 — Pending Damage Claim of Ansin Sloat-Davis
- Start: 05:13:35 (YouTube)
- Action: Executive session summary read into record
- Vote: N/A
- Notes: No action needed in open session
Item 28 — Employment Review of City Manager John Ratliff
- Start: 05:13:55 (YouTube)
- Action: Executive session summary read into record
- Vote: N/A
- Notes: No action needed in open session
Item 29 — Joseph Gonzalez, as Personal Representative of the Estate of Tshante Gonzalez, Deceased v. City of Lawton, et al.
- Start: 05:14:10 (YouTube)
- Action: Executive session summary read into record
- Vote: N/A
- Notes: No action needed in open session
Audience Participation
Audience Participation
- Start: 05:14:47 (YouTube)
- Action: Mayor announced one speaker request; no speaker present
- Vote: N/A
- Notes: Zeb Hendris was called but not present
Adjournment
Adjournment
- Start: 05:15:02 (YouTube)
- Action: Motion to adjourn approved
- Vote: Roll call vote; adjournment approved
- End: 05:15:12 (YouTube)
- Notes: Meeting adjourned